The fish barrier will be constructed in two phases. In the first phase the creek
is diverted to the west side of the canyon to allow the eastern half of the
structure to be formed, poured and cured. Although this phase will allow for
the construction of the biggest portion of the barrier it is the easier of the two
required creek diversions. In this phase, water need only be pushed to the
side. In the upcoming phase two, the water will be diverted to the side, up and
over the finished first half of the barrier. The pictures below are excavating
and creek diversion for phase I.